One programme,
one site team.

Flooring, lighting, poles and nets from one contractor — so there is one sequence, one crew, and one person answerable for the result. 11 steps, in the order they happen on site.

Bundles of sawn teak stacked in a finished room, waiting to be laid

01

Set out

Where the court sits in the hall, and whether the run-off around it works before anything is fixed to the floor.

  1. 01

    Survey & set-out

    Site measured, levels taken, court positions set out to international dimensions.

02

The base

What the framework stands on: a sealed substrate, a moisture-resistant membrane, and the pads that take the impact.

  1. 02

    Base preparation

    Concrete substrate prepared and sealed with a 3–5 mm moisture-resistant membrane.

  2. 03

    Shock pads

    20–21 mm button-type pads set out across the base for vibration absorption.

03

The framework

Whether what goes down is one continuous timber framework or a set of individual supports. Both directions, interlocked at every crossing.

  1. 04

    First pine direction

    Chemically treated pine members laid across the base in the first direction.

  2. 05

    Second pine direction & interlocking

    Perpendicular members brought in and interlocked at every intersection, forming one continuous framework.

  3. 06

    Pneumatic nailing

    The entire wood-flooring work processing is carried out using pneumatic nailing machines only.

04

The floor

The plane. Boards go straight onto the framework and are blind-nailed through the tongue; the sanding after them is what makes the surface true.

  1. 07

    Flooring

    20–21 mm African teak, or maple for squash, laid tongue-and-groove and blind-nailed through the tongue directly onto the framework.

  2. 08

    Industrial sanding & finish

    Industrial sanding and finish, then sealed with a water-based PU court finish.

Nets up on a finished court, a blue-clad hall around it

05

Handover

What gets played on and what gets billed: markings to international dimensions, freestanding poles and nets, lighting, and a final measurement of the court as built.

  1. 09

    Markings, poles & nets

    Court lines set out to international dimensions; professional poles and nets installed.

  2. 10

    Lighting

    150W fixtures and supports installed and positioned for glare-free play.

  3. 11

    Measurement & handover

    Final measurements taken post-completion; billing based on actual site dimensions.

After handover

Billed on the court that got built.

Final measurements are taken after completion and billing follows the actual site dimensions — not the ones on the drawing. The same sequence has run 99 courts across 31 sites.